A bridge too far in Himachal Pradesh!


In June 2009, Gammon stopped decking work on the ground that strata around the pier was not the same as envisaged during designing the foundation.

However, launching of deck slab continued till January 2010 and the firm thereafter stopped the work.

In June 2011, the firm got the geological investigation of the bridge site done by the Indian Institute of Technology-Roorkee.

The IIT-R said it would be advisable to look for an alternate location for the bridge.

Considering the quantum of work executed, the time involved and the expenditure incurred, it however suggested a deep-seated foundation on firm strata at a depth of 20m.

The CAG said Gammon India again got a geotechnical investigation and bathymetric survey conducted in September 2011 from another agency. Based on its investigation, a revised proposal for the foundation of bridge piers was submitted.

The revised proposal was, however, not approved by the PWD till last May.

"The PWD in December 2011 granted extension of time up to March 2012 to keep the contract agreement alive. But it levied seven percent compensation of Rs.1.6 crore (on the firm) for delay in completion of work, which amount too was also not received till August 2012," said the CAG, in a report tabled in the state assembly last week.

Till March 2012, 61 percent of the construction work had been completed.

The PWD failure to accord technical sanction for the bridge construction and ensuring adequate geological investigation before awarding the work contributed to a delay in completion of the work for more than three years, the CAG report said.